State Route 383 – Rochester, NY

Rochester, NY - 2015

Project Description

NY District 4 wanted to find a substitute for their costly deep mill repair used to fix their transverse reflective cracking problem caused by an old (1930s) concrete base. FORTA-FI® was placed in the driving lane of Route 383 – this section of highway experiences heavy truck traffic, 70% of which is in the driving lane. The old way of construction required a 6” deep mill to be filled with polymerized asphalt. The fiber side was simply a 2” mill/fill and was completed in about 2-3 weeks. On this project, there were over 17 locations where the control side cracked and the fiber side did not. Using FORTA-FI® saved the project over 4 weeks of construction time, in lieu of the deep mill repair.

Update

After 2 years, both lanes had benefited from a crack seal. However, the FORTA-FI reinforced side did not have cracks, but the typical joint repairs and the standard HMA overlay did. After 7 years and 2 inspection cycles, this composite roadway was inspected again to determine the current PCI (Pavement Condition Index). The average for the FORTAfied™ side was about 8 points higher than the east bound control side. This confirmed that the cracking was delayed by at least 2 years. Using FORTA reinforcement fibers saved 10% in initial project costs and has been confirmed to be more effective in stopping reflective cracking. These savings also do not include reductions in traffic control or savings to the general public.

Key Points

  • Saved Money
  • Saved Construction Time
  • Reduced Cracking

Download PDF

Calculate Your Savings!
Select Unit:US TonMetric Ton
Enter Asphalt:

Enter Asphalt Price:
FORTAfied asphalt for Tons of Savings!

Use our Savings Calculator to compare material costs between a traditional asphalt mixture and FORTAfied Asphalt.

Original Asphalt Cost:

Reduction in Asphalt Thickness:

Reduced Asphalt Cost:
Cost of FORTA-FI (based on MSRP):

FORTAfied Asphalt Cost =

Material Cost Savings =
Savings in Tons =